JAL JEEVAN MISSION - Pipe line extension , providing FHTC , Construction of OHSR in Kummil Panchayath - Phase II

Project JAL JEEVAN MISSION - Pipe line extension , providing FHTC , Construction of OHSR in Kummil Panchayath - Phase II
Project Code KLMJJM08204155
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Pipe line extension , providing FHTC , Construction of OHSR
Status Completed
District Kollam
Executing Office Kadakkal PH Sn
AS Amount (Rs) 202580000
AS Number GO(Rt) no 541/2020 of 2021-2022
TS Amount (Rs) 168850000
TS Number TS/2021-2022/2020/20662
Total Bill Submitted (Rs) 148006119
Total Bill Paid (Rs) 1390322590
Population Benefitted 19900
Capacity in MLD 2.00
Actual Project Completion Date 31 Mar 2025
Coverage FHTC in Kummil Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JAL JEEVAN MISSION - Pipe line extension , providing FHTC , Construction of OHSR in Kummil Panchayath - Phase II Kadakkal PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Aug 2025 Work Completed Kadakkal PH Sn - AE
25 Aug 2025 Charging, commissioning and leak rectification Kadakkal PH Sn - AE
16 Aug 2025 Charging, commissioning and leak rectification Kadakkal PH Sn - AE
06 Aug 2025 Charging, commissioning and leak rectification Kadakkal PH Sn - AE
28 Jul 2025 Physically work completed. Charging commissioning and leak rectifications ongoing Kadakkal PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/04/2022
Scheduled date of Completion of the Project 25 Jul 2023
Expected date of Completion 31/03/2025

Processing Dates

AS Date 21 Aug 2020
TS Date 31 May 2021

Other details

Project Officers View