| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Apr 2024 | PVC Pipe Laying | Kadakkal PH Sn - AE | |
| 30 Mar 2024 | Road Restoration | Kadakkal PH Sn - AE | |
| 04 Mar 2024 | Anchor Block Work and Road Restoration | Kadakkal PH Sn - AE | |
| 02 Mar 2024 | Column Plastering of Kummil OHSR at Anchumalakunnu | Kadakkal PH Sn - AE | |
| 23 Feb 2024 | Hand Rail Fixing in Kummil OHSR at Anchumalakunnu | Kadakkal PH Sn - AE | |
| 21 Feb 2024 | Side Wall Plastering of Kummil OHSR at Anchumalakunnu | Kadakkal PH Sn - AE | |
| 10 May 2024 | House Connections | Kadakkal PH Sn - AE | |
| 09 May 2024 | House Connections | Kadakkal PH Sn - AE | |
| 06 May 2024 | PVC Pipe Laying at Pangalukadu | Kadakkal PH Sn - AE | |
| 17 Apr 2024 | GI Gap Works | Kadakkal PH Sn - AE |