Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Jun 2023 | 379 FHTC & 71 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid. | Perinthalmanna AE | |
24 Jun 2023 | 379 FHTC & 71 HTC given. 8500m 250mm DI laid. 110mm PE 1918.2m laid. 90mm PE 13531.7m laid. 160mm HDPE 2500m laid. | Perinthalmanna AE | |
22 Jun 2023 | 362 FHTC & 73 HTC given. 8000m 250mm DI laid. 110mm PE 1418.2m laid. 90mm PE 13331.7m laid. 160mm HDPE 2325.9 laid. | Perinthalmanna AE | |
21 Jun 2023 | 315 FHTC & 70 HTC given. 7506m 250mm DI laid. 110mm PE 1318.2m laid. 90mm PE 13131.7m laid.160mm HDPE 2225.9 laid. | Perinthalmanna AE | |
20 Jun 2023 | 309 FHTC & 59 HTC given. 3220.7m 250mm DI laid. 110mm PE 917m laid. 90mm PE 11693m laid.160mm PVC 75m laid.160mm HDPE 170m laid. 279 FHTC Bill Submitted,67 HTC Bill Submitted. | Perinthalmanna AE | |
19 Jun 2023 | 309 FHTC & 59 HTC given. 3220.7m 250mm DI laid. 110mm PE 917m laid. 90mm PE 11693m laid.160mm PVC 75m laid.160mm HDPE 170m laid. 279 FHTC Bill Submitted,67 HTC Bill Submitted. | Perinthalmanna AE | |
14 Jun 2023 | 309 FHTC & 59 HTC given. 3220.7m 250mm DI laid. 110mm PE 917m laid. 90mm PE 11693m laid.160mm PVC 75m laid.160mm HDPE 170m laid. 279 FHTC Bill Submitted,67 HTC Bill Submitted. | Perinthalmanna AE | |
12 Jun 2023 | 309 FHTC & 59 HTC given. 3220.7m 250mm DI laid. 110mm PE 917m laid. 90mm PE 11693m laid.160mm PVC 75m laid.160mm HDPE 170m laid. 279 FHTC Bill Submitted,67 HTC Bill Submitted. | Perinthalmanna AE | |
08 Jun 2023 | 309 FHTC & 59 HTC given. 3220.7m 250mm DI laid. 110mm PE 917m laid. 90mm PE 11693m laid.160mm PVC 75m laid.160mm HDPE 170m laid. 279 FHTC Bill Submitted,67 HTC Bill Submitted. | Perinthalmanna AE | |
07 Jun 2023 | 309 FHTC & 59 HTC given. 3220.7m 250mm DI laid. 110mm PE 917m laid. 90mm PE 11693m laid.160mm PVC 75m laid.160mm HDPE 170m laid. 279 FHTC Bill Submitted,67 HTC Bill Submitted. | Perinthalmanna AE |