Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
12 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
11 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
08 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
07 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
05 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
04 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
02 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
01 Sep 2023 442 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
26 Aug 2023 441 FHTC & 163 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE