Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission-2020-21 - Providing functional house hold Tap connections in Pulamanthole Grama Panchayath-Phase-2

Project Jal Jeevan Mission-2020-21 - Providing functional house hold Tap connections in Pulamanthole Grama Panchayath-Phase-2
Project Code MLPJJM12209080
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Pipe Line Extension, FHTCs-4332 Pumpset
Status On-going
District Malappuram
Executing Office Malappuram PH Dn
AS Amount (Rs) 153000000
AS Number G.O.(Rt)No.777/2020/WRD
TS Amount (Rs) 149900000
TS Number Reg .No. 13920/2021-2022
Total Bill Submitted (Rs) 32160128
Total Bill Paid (Rs) 27187877
Population Benefitted 22000
Capacity in MLD 0.00
Actual Project Completion Date Date is not specified
Coverage 8000
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission-2020-21- Providing functional house hold Tap connections in Pulamanthole Grama Panchayath-Phase-2 Perinthalmanna PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 899 FHTC &66 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm HDPE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
15 Jun 2024 843 FHTC &62 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm HDPE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
10 Jun 2024 843 FHTC &62 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm HDPE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
06 Jun 2024 843 FHTC &62 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm HDPE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
27 May 2024 843 FHTC &62 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm HDPE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/02/2022
Scheduled date of Completion of the Project 02 Nov 2022
Expected date of Completion 30/09/2023

Processing Dates

AS Date 24 Dec 2020
TS Date 26 Nov 2021

Other details

Project Officers View