Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 Aug 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
08 Aug 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
07 Aug 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
04 Aug 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
03 Aug 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
02 Aug 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
01 Aug 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
31 Jul 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
29 Jul 2023 | 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE | |
27 Jul 2023 | 404 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid | Perinthalmanna AE |