10 Aug 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
08 Aug 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
07 Aug 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
04 Aug 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
03 Aug 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
02 Aug 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
01 Aug 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
31 Jul 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
29 Jul 2023 417 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE
27 Jul 2023 404 FHTC & 122 HTC given. 9000m 250mm DI laid. 110mm PE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid Perinthalmanna AE