| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Mar 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 11 Mar 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 10 Mar 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 07 Mar 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 06 Mar 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 05 Mar 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 03 Mar 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 01 Mar 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 28 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 25 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE |