| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Aug 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given.Delay due to water looging | Kollam WS Sn 1 - AE | |
| 11 Aug 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given.Delay due to water looging | Kollam WS Sn 1 - AE | |
| 08 Aug 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given.Delay due to heavy rain fall and water looging | Kollam WS Sn 1 - AE | |
| 31 Jul 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given.Delay due to heavy rain fall and water looging | Kollam WS Sn 1 - AE | |
| 29 Jul 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given.Delay due to heavy rain fall and water looging | Kollam WS Sn 1 - AE | |
| 23 Jul 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given.Delay due to heavy rain fall and water looging | Kollam WS Sn 1 - AE | |
| 21 Jul 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given.Delay due to heavy rain fall and water looging | Kollam WS Sn 1 - AE | |
| 19 Jul 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 15 Jul 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 10 Jul 2025 | 79 % completed, 3669.1 m pipe laid, 133 nos alterations are given. | Kollam WS Sn 1 - AE |