| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Jun 2025 | 68 % completed, 3156 m pipe laid, 133 nos alterations are given | Kollam WS Sn 1 - AE | |
| 09 Jun 2025 | 68 % completed, 3156 m pipe laid, 133 nos alterations are given | Kollam WS Sn 1 - AE | |
| 02 Jun 2025 | 68 % completed, 3156 m pipe laid, 133 nos alterations are given | Kollam WS Sn 1 - AE | |
| 30 May 2025 | 68 % completed, 3156 m pipe laid, 133 nos alterations are given | Kollam WS Sn 1 - AE | |
| 27 May 2025 | 68 % completed, 3156 m pipe laid, 133 nos alterations are given | Kollam WS Sn 1 - AE | |
| 22 May 2025 | 68 % completed, 3156 m pipe laid, 126 nos alterations are given | Kollam WS Sn 1 - AE | |
| 17 May 2025 | 68 % completed, 3156 m pipe laid, 126 nos alterations are given | Kollam WS Sn 1 - AE | |
| 16 May 2025 | 68 % completed, 3156 m pipe laid, 126 nos alterations are given | Kollam WS Sn 1 - AE | |
| 14 May 2025 | 68 % completed, 3156 m pipe laid, 126 nos alterations are given | Kollam WS Sn 1 - AE | |
| 12 May 2025 | 68 % completed, 3156 m pipe laid, 126 nos alterations are given | Kollam WS Sn 1 - AE |