| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Jan 2026 | 99 % completed, 5430 m pipe laid, 236 nos alterations are given | Kollam WS Sn 1 - AE | |
| 12 Jan 2026 | 99 % completed, 5430 m pipe laid, 236 nos alterations are given | Kollam WS Sn 1 - AE | |
| 09 Jan 2026 | 99 % completed, 5430 m pipe laid, 236 nos alterations are given | Kollam WS Sn 1 - AE | |
| 07 Jan 2026 | 99 % completed, 5430 m pipe laid, 236 nos alterations are given | Kollam WS Sn 1 - AE | |
| 03 Jan 2026 | 99 % completed, 5430 m pipe laid, 236 nos alterations are given | Kollam WS Sn 1 - AE | |
| 31 Dec 2025 | 88 % completed, 4077.8 m pipe laid, 178 nos alterations are given.Delay due to water logging | Kollam WS Sn 1 - AE | |
| 29 Dec 2025 | 88 % completed, 4077.8 m pipe laid, 178 nos alterations are given.Delay due to water logging | Kollam WS Sn 1 - AE | |
| 26 Dec 2025 | 88 % completed, 4077.8 m pipe laid, 178 nos alterations are given.Delay due to water logging | Kollam WS Sn 1 - AE | |
| 23 Dec 2025 | 88 % completed, 4077.8 m pipe laid, 178 nos alterations are given.Delay due to water logging | Kollam WS Sn 1 - AE | |
| 16 Dec 2025 | 88 % completed, 4077.8 m pipe laid, 178 nos alterations are given.Delay due to water logging | Kollam WS Sn 1 - AE |