Status Date Overall Project Status Project Officer Contact
06 May 2025 68 % completed, 3156 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
03 May 2025 68 % completed, 3156 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
28 Apr 2025 68 % completed, 3156 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
19 Apr 2025 68 % completed, 3156 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
16 Apr 2025 68 % completed, 3156 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
15 Apr 2025 68 % completed, 3156 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
05 Apr 2025 22 % completed, 1019 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
03 Apr 2025 22 % completed, 1019 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
01 Apr 2025 22 % completed, 1019 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE
29 Mar 2025 22 % completed, 1019 m pipe laid, 126 nos alterations are given Kollam WS Sn 1 - AE