| 11 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 09 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 08 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 05 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 03 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 02 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 01 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 30 Oct 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |