| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Dec 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 07 Dec 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 06 Dec 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 04 Dec 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 02 Dec 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 02 Dec 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 30 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 29 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 27 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 26 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE |