| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 24 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 22 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 22 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 20 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 19 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 18 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE | |
| 18 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 15 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Vadanappilly AE | |
| 15 Nov 2021 | Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval. Package VI pipe supplied. awaiting PWD Road cutting permission | Mathilakam AE |