| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Dec 2025 | 400mm DI - 2268m completed, 500mm DI - 1140m | Vadanappilly AE | |
| 18 Jul 2025 | Meeting held at thrissur collectorate regarding pipe unloading and laying. | Vadanappilly AE | |
| 15 Jul 2025 | Agreement yet to be executed | Vadanappilly AE | |
| 13 May 2025 | Estimate and other documents submitted for Goverment Approval | Chalakudy AE 1 | |
| 25 Jan 2025 | Estimate and other documents submitted for Goverment Approval | Mathilakam AE | |
| 22 Jan 2025 | Estimate and other documents submitted for Goverment Approval | Mathilakam AE | |
| 04 Jan 2025 | Estimate and other documents submitted for Goverment Approval | Mathilakam AE | |
| 31 Dec 2024 | Estimate and other documents submitted for Goverment Approval | Mathilakam AE | |
| 13 Dec 2024 | Estimate and other documents submitted for Goverment Approval | Mathilakam AE | |
| 03 Dec 2024 | Estimate and other documents submitted for Goverment Approval | Mathilakam AE |