Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 14.50km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering in progress. FHTCs -131Numbers Completed.Reinforcement work of floor beam in progress. | Kollam Project HD | |
30 Aug 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 14.50km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering in progress. FHTCs -131Numbers Completed | Kollam Project HD | |
29 Aug 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 14.50km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering in progress. FHTCs -131Numbers Completed | Kollam Project HD | |
27 Aug 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 13km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering in progress. FHTCs -131Numbers Completed | Kollam Project HD | |
24 Aug 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 12km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering in progress. FHTCs -131Numbers Completed | Kollam Project HD | |
20 Aug 2022 | DI laying 635m completed . HDPE laying in progress, 10.5km completed. Columns upto floor level completed. Floor beam and slab shuttering in progress. | Kollam Project HD | |
26 May 2022 | excavation works for OHSR works started | Kollam Project HD | |
27 Feb 2022 | One offer received on retender. Bid send for PQ to circle office on 23.02.2022. | Kollam Project Dn EE | |
01 Feb 2022 | Tender extended upto 14.02.2022 due to non participation. | Kollam Project HD |