Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 16 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -184 Numbers Completed. Haunch column concrete completed.Side wall concreting in progress. | Kollam Project HD | |
20 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 16 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concreting work in progress. FHTCs -184 Numbers Completed. | Kollam Project HD | |
18 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 16 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concreting work in progress. FHTCs -131 Numbers Completed. | Kollam Project HD | |
14 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 15 km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering work completed.FHTCs -131Numbers Completed.Floor beam concreting completed.Reinforcement work of floor slab completed. HDPE laying work in progress.Floor slab concreting completed. | Kollam Project HD | |
13 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 15 km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering work completed.FHTCs -131Numbers Completed.Floor beam concreting completed.Reinforcement work of floor slab completed. HDPE laying work in progress.Floor slab concrete in progress. | Kollam Project HD | |
12 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 15 km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering work completed.FHTCs -131Numbers Completed.Floor beam concreting completed.Reinforcement work of floor slab in progress. HDPE laying work in progress. | Kollam Project HD | |
07 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 15 km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering work completed.FHTCs -131Numbers Completed.Floor beam concreting completed.Reinforcement work of floor slab in progress. HDPE laying work in progress. | Kollam Project HD | |
05 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 15 km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering work completed.FHTCs -131Numbers Completed.Floor beam concreting Completed.Reinforcement work of floor slab in progress. HDPE laying work in progress. | Kollam Project HD | |
02 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 14.50km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering work completed.FHTCs -131Numbers Completed.Floor beam concreting completed. | Kollam Project HD | |
01 Sep 2022 | 200mm DI K9 CWPM - 635m laying completed.Distribution network - pipe laying in progress, 14.50km completed. 7LL OHSR - Columns upto floor level completed. Floor beam and slab shuttering work completed.FHTCs -131Numbers Completed.Reinforcement work of floor beam in progress. | Kollam Project HD |