Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -216 Numbers Completed .Side wall concreting completed. | Kollam Project HD | |
15 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -216 Numbers Completed .Side wall concreting completed. | Kollam Project HD | |
14 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -216 Numbers Completed .Side wall concreting completed. | Kollam Project HD | |
13 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -216 Numbers Completed.Side wall concreting in progress. | Kollam Project HD | |
12 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -205 Numbers Completed.Side wall concreting in progress. | Kollam Project HD | |
11 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -205 Numbers Completed.Side wall concreting in progress. | Kollam Project HD | |
10 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -205 Numbers Completed.Side wall concreting in progress. | Kollam Project HD | |
09 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 18 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -184 Numbers Completed.Side wall concreting in progress. | Kollam Project HD | |
08 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 18 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -184 Numbers Completed.Side wall concreting in progress. | Kollam Project HD | |
07 Oct 2022 | 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 18 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -184 Numbers Completed.Side wall concreting in progress. | Kollam Project HD |