Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -216 Numbers Completed .Side wall concreting completed. Kollam Project HD
15 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -216 Numbers Completed .Side wall concreting completed. Kollam Project HD
14 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -216 Numbers Completed .Side wall concreting completed. Kollam Project HD
13 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -216 Numbers Completed.Side wall concreting in progress. Kollam Project HD
12 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -205 Numbers Completed.Side wall concreting in progress. Kollam Project HD
11 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -205 Numbers Completed.Side wall concreting in progress. Kollam Project HD
10 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 19 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -205 Numbers Completed.Side wall concreting in progress. Kollam Project HD
09 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 18 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -184 Numbers Completed.Side wall concreting in progress. Kollam Project HD
08 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 18 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -184 Numbers Completed.Side wall concreting in progress. Kollam Project HD
07 Oct 2022 200mm DI K9 CWPM - 635m laying completed. Distribution network - pipe laying work in progress, 18 km completed. 7LL OHSR - RCC work up to Floor slab completed. Inside column concrete completed. FHTCs -184 Numbers Completed.Side wall concreting in progress. Kollam Project HD