Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Jun 2024 | Pipe Laid 880 m out of 3750 m and FHTC 100 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
20 Jun 2024 | Pipe Laid 880 m out of 3750 m and FHTC 100 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
17 Jun 2024 | Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
14 Jun 2024 | Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
11 Jun 2024 | Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
08 Jun 2024 | Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
05 Jun 2024 | Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
02 Jun 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
30 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
27 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 |