Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Jun 2024 Pipe Laid 880 m out of 3750 m and FHTC 100 Nos out of 250 Nos completed. Kannur WS Sn AE 2
20 Jun 2024 Pipe Laid 880 m out of 3750 m and FHTC 100 Nos out of 250 Nos completed. Kannur WS Sn AE 2
17 Jun 2024 Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. Kannur WS Sn AE 2
14 Jun 2024 Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. Kannur WS Sn AE 2
11 Jun 2024 Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. Kannur WS Sn AE 2
08 Jun 2024 Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. Kannur WS Sn AE 2
05 Jun 2024 Pipe Laid 880 m out of 3750 m and FHTC 95Nos out of 250 Nos completed. Kannur WS Sn AE 2
02 Jun 2024 Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
30 May 2024 Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
27 May 2024 Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2