Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Apr 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
20 Apr 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
17 Apr 2024 | Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
14 Apr 2024 | Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
11 Apr 2024 | Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
08 Apr 2024 | Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
05 Apr 2024 | Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
02 Apr 2024 | Pipe Laid 468m out of 3750 m. | Kannur WS Sn AE 2 | |
30 Mar 2024 | Pipe Laid 468m out of 3750 m. | Kannur WS Sn AE 2 | |
27 Mar 2024 | Pipe Laid 468m out of 3750 m. | Kannur WS Sn AE 2 |