Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
20 Apr 2024 Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
17 Apr 2024 Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
14 Apr 2024 Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
11 Apr 2024 Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
08 Apr 2024 Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
05 Apr 2024 Pipe Laid 468 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. Kannur WS Sn AE 2
02 Apr 2024 Pipe Laid 468m out of 3750 m. Kannur WS Sn AE 2
30 Mar 2024 Pipe Laid 468m out of 3750 m. Kannur WS Sn AE 2
27 Mar 2024 Pipe Laid 468m out of 3750 m. Kannur WS Sn AE 2