Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
21 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
18 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
15 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
12 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
09 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
06 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
03 May 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
30 Apr 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 | |
27 Apr 2024 | Pipe Laid 760 m out of 3750 m and FHTC 80 Nos out of 250 Nos completed. | Kannur WS Sn AE 2 |