Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Dec 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.90%completed.Connection=35.89%completed | Chalakudy AE 2 | |
29 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.85%completed.Connection=35.89%completed | Chalakudy AE 2 | |
28 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.80%completed.Connection=35.89%completed | Chalakudy AE 2 | |
25 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.80%completed.Connection=35.89%completed | Chalakudy AE 2 | |
22 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.80%completed.Connection=35.89%completed | Chalakudy AE 2 | |
21 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.80%completed.Connection=35.89%completed | Chalakudy AE 2 | |
20 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.80%completed.Connection=35.89%completed | Chalakudy AE 2 | |
20 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.70%completed.Connection=35.89%completed | Chalakudy AE 2 | |
16 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.70%completed.Connection=35.89%completed | Chalakudy AE 2 | |
15 Nov 2023 | WORK IN PROGRESS.1213 connection tagged. pipe supplied 95.60%.laying = 51.70%completed.Connection=35.89%completed | Chalakudy AE 2 |