Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Sep 2023 | WORK IN PROGRESS.1173 connection tagged.pipe supplied 95.60%.laying = 51.70%completed.Connection=34.71%completed | Chalakudy AE 2 | |
22 Sep 2023 | WORK IN PROGRESS.1173 connection tagged.pipe supplied 95.60%.laying = 51.70%completed.Connection=34.71%completed | Chalakudy AE 2 | |
21 Sep 2023 | WORK IN PROGRESS.1173 connection tagged.pipe supplied 95.60%.laying = 51.70%completed.Connection=34.71%completed | Chalakudy AE 2 | |
20 Sep 2023 | WORK IN PROGRESS.1173 connection tagged.pipe supplied 95.60%.laying = 51.70%completed.Connection=34.71%completed | Chalakudy AE 2 | |
16 Sep 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
15 Sep 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
13 Sep 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
07 Sep 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
05 Sep 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
04 Sep 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 |