Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Sep 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
25 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
23 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
21 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 79.24%.laying = 51.70%completed.Connection=19.76%completed | Chalakudy AE 2 | |
19 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed. | Chalakudy AE 2 | |
18 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed. | Chalakudy AE 2 | |
17 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed. | Chalakudy AE 2 | |
16 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed. | Chalakudy AE 2 | |
14 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed. | Chalakudy AE 2 | |
11 Aug 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 |