Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Jan 2024 | WORK IN PROGRESS.1266 connection tagged. pipe supplied 95.60%.laying = 60.75%completed.Connection=36.28%completed | Chalakudy AE 2 | |
10 Jan 2024 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 60.70%completed.Connection=36.28%completed | Chalakudy AE 2 | |
09 Jan 2024 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 60.70%completed.Connection=36.28%completed | Chalakudy AE 2 | |
08 Jan 2024 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 60.20%completed.Connection=36.28%completed | Chalakudy AE 2 | |
06 Jan 2024 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 60.20%completed.Connection=36.28%completed | Chalakudy AE 2 | |
05 Jan 2024 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 60.20%completed.Connection=36.28%completed | Chalakudy AE 2 | |
04 Jan 2024 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 60.20%completed.Connection=36.28%completed | Chalakudy AE 2 | |
31 Dec 2023 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 60.10%completed.Connection=36.28%completed | Chalakudy AE 2 | |
30 Dec 2023 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 51.95%completed.Connection=36.28%completed | Chalakudy AE 2 | |
29 Dec 2023 | WORK IN PROGRESS.1226 connection tagged. pipe supplied 95.60%.laying = 51.95%completed.Connection=36.28%completed | Chalakudy AE 2 |