Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
27 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
26 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
25 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
24 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
22 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
20 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
19 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
15 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
14 Jul 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 |