Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
14 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
13 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
12 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
09 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
08 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
07 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
06 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
05 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 | |
03 Jun 2023 | WORK IN PROGRESS.715 connection tagged.pipe supplied 71.80%.laying = 45.010%completed.Connection=19.76%completed | Chalakudy AE 2 |