Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 May 2023 | CC first and part bill submitted | Chalakudy AEE | |
15 May 2023 | Inauguration of JJM PHASE 2 conducted on 15.05.2023, by Honourable MLA Sri. K. K. Ramachandran. House connection given to Mr. Benny Alookkaran, Ward 2 | Ollur AE | |
11 May 2023 | CC 1st & Part bill submitted | Ollur AE | |
10 May 2023 | Work in progress-63mm PVC -90m pipe laid in ward 3,Ashoka road | Ollur AE | |
06 May 2023 | Work in progress-63mm PVC -90m pipe laid in ward 3,Ashoka road | Ollur AE | |
03 May 2023 | Work in progress-63mm PVC -204m pipe laid,ward 12-Ashoka road | Ollur AE | |
01 May 2023 | Work started | Ollur AE | |
29 Apr 2023 | Pipe supplied. Work not started | Ollur AE | |
17 Apr 2023 | Pipe supplied. Work not started | Ollur AE | |
10 Apr 2023 | Pipe supplied | Ollur AE |