Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Jul 2023 | Work in Progress,63mm PVC ,90mm HDPE,75mm PVC,110mm HDPE,Total 8056m Ward7,810,11,12 | Ollur AE | |
19 Jul 2023 | Work in Progress (90mm HDPE Pipe-290m),Total 6590m Ward7,10,11,12 | Ollur AE | |
14 Jul 2023 | Work in Progress | Ollur AE | |
10 Jul 2023 | Work in Progress | Ollur AE | |
06 Jul 2023 | Work in Progress | Ollur AE | |
04 Jul 2023 | Work in Progress 63mm PVC ,75mm PVC ,90mm,110mm HDPE HDPE PIPE 6300m WARD 7,10,11,12 | Ollur AE | |
30 Jun 2023 | Work in Progress 63mm PVC ,75mm PVC ,90mm,110mm HDPE HDPE PIPE 6282M WARD 7,10,11,12 | Ollur AE | |
26 Jun 2023 | Work in Progress 63mm PVC ,75mm PVC ,90mm HDPE PIPE 5662M WARD 7,10,12 | Ollur AE | |
24 Jun 2023 | Work in Progress 63mm PVC ,75mm PVC ,90mm HDPE PIPE 5294M WARD 7,10,12 | Ollur AE | |
19 Jun 2023 | Work in Progress 63mm PVC ,75mm PVC ,90mm HDPE PIPE 3000M WARD 7,10,12 | Ollur AE |