Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Dec 2023 | Work in Progress, TOTAL-17147 m Pipe laid . Total connection -171 nos (Geo tagged 142 nos) | Ollur AE | |
25 Nov 2023 | Work in Progress, TOTAL-15112m Pipe laid . Total connection -151 nos (Geo tagged 125 nos) | Ollur AE | |
21 Nov 2023 | Work in Progress110mm HDPE Pipe-laying in ward 4 -391m,TOTAL-14861m Total connection -151 nos (Geo tagged 108 nos) | Ollur AE | |
14 Nov 2023 | Work in Progress110mm HDPE Pipe-laying in ward 4 -391m,TOTAL-14861m Total connection -151 nos (Geo tagged 108 nos) | Ollur AE | |
09 Nov 2023 | Work in Progress110mm HDPE Pipe-laying in ward 4 -391m,TOTAL-14861m Total connection -151 nos (Geo tagged 108 nos) | Ollur AE | |
04 Nov 2023 | Work in Progress110mm HDPE Pipe-laying in ward 4 -391m,TOTAL-14861m Total connection -151 nos (Geo tagged 108 nos) | Ollur AE | |
26 Oct 2023 | Work in Progress110mm HDPE Pipe-laying in ward 4 -391m,TOTAL-14861m Total connection -151 nos (Geo tagged 108 nos) | Ollur AE | |
21 Oct 2023 | Work in Progress110mm HDPE Pipe-laying in ward 4 -391m,TOTAL-14861m Total connection -151 nos (Geo tagged 108 nos) | Ollur AE | |
16 Oct 2023 | Work in Progress110mm HDPE Pipe-laying in ward 4 -391m,TOTAL-14861m Total connection -151 nos (Geo tagged 108 nos) | Ollur AE | |
04 Oct 2023 | Work in Progress110mm HDPE Pipe-laying in ward 4 -391m,TOTAL-14861m Total connection -151 nos (Geo tagged 108 nos) | Ollur AE |