Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Jun 2023 | Work in Progress 63mm PVC ,75mm PVC ,90mm HDPE PIPE 3000M WARD 7,10,12 | Ollur AE | |
07 Jun 2023 | 90mm HDPE Pipe Laid-80m @ ward 12 | Ollur AE | |
05 Jun 2023 | 75mm PVC 6kg/cm2 Laid 36m @ward 12 | Ollur AE | |
04 Jun 2023 | 75mm PVC 6kg/cm2 Laid 42m @ward 12 | Ollur AE | |
31 May 2023 | 63mm PVC 6kg/cm2 Laid 78m @ward 7 | Ollur AE | |
30 May 2023 | 75mm PVC 6kg/cm2 Laid 36m,63mm PVC 6kg/cm2 Laid 132m @ward 7 | Ollur AE | |
29 May 2023 | Interconnection work done @ ward 3 for giving house connections | Ollur AE | |
26 May 2023 | 63mm PVC 6kg/cm2 laid 636m. 75mm PVC 6kg/cm2 laid 180m. 90mm HDPE 730m laid. | Ollur AE | |
22 May 2023 | CC first and part bill submitted | Ollur AE | |
20 May 2023 | CC first and part bill submitted | Ollur AE |