Status Date Overall Project Status Project Officer Contact
01 Mar 2024 PACKAGE 1- SITE HANDED OVER and disconnection list given( 1 % COMPLETED. PACKAGE 2-40 % COMPLETED ( 170 NOS. OF TAP DISCONNECTED ) Kollam WS Sn 2 - AE
26 Feb 2024 PACKAGE 1- SITE HANDED OVER and disconnection list given( 1 % COMPLETED. PACKAGE 2-40 % COMPLETED ( 170 NOS. OF TAP DISCONNECTED ) Kollam WS Sn 2 - AE
21 Feb 2024 PACKAGE 1- SITE HANDED OVER and disconnection list given( 1 % COMPLETED. PACKAGE 2- 25 % COMPLETED ( 130 NOS. OF TAP DISCONNECTED ) Kollam WS Sn 2 - AE
17 Feb 2024 PACKAGE 1- SITE HANDED OVER and disconnection list given( 1 % COMPLETED. PACKAGE 2- 25 % COMPLETED ( 130 NOS. OF TAP DISCONNECTED ) Kollam WS Sn 2 - AE
15 Feb 2024 PACKAGE 1- SITE HANDED OVER( 1 % COMPLETED. PACKAGE 2- 25 % COMPLETED ( 130 NOS. OF TAP DISCONNECTED ) Kollam WS Sub Dn - AEE
15 Feb 2024 SITE HANDED OVER Kollam WS Sub Dn - AEE
15 Feb 2024 SITE HANDED OVER Kollam WS Sub Dn - AEE