| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Mar 2024 | PACKAGE 1- SITE HANDED OVER and disconnection list given( 1 % COMPLETED. PACKAGE 2-40 % COMPLETED ( 170 NOS. OF TAP DISCONNECTED ) | Kollam WS Sn 2 - AE | |
| 26 Feb 2024 | PACKAGE 1- SITE HANDED OVER and disconnection list given( 1 % COMPLETED. PACKAGE 2-40 % COMPLETED ( 170 NOS. OF TAP DISCONNECTED ) | Kollam WS Sn 2 - AE | |
| 21 Feb 2024 | PACKAGE 1- SITE HANDED OVER and disconnection list given( 1 % COMPLETED. PACKAGE 2- 25 % COMPLETED ( 130 NOS. OF TAP DISCONNECTED ) | Kollam WS Sn 2 - AE | |
| 17 Feb 2024 | PACKAGE 1- SITE HANDED OVER and disconnection list given( 1 % COMPLETED. PACKAGE 2- 25 % COMPLETED ( 130 NOS. OF TAP DISCONNECTED ) | Kollam WS Sn 2 - AE | |
| 15 Feb 2024 | PACKAGE 1- SITE HANDED OVER( 1 % COMPLETED. PACKAGE 2- 25 % COMPLETED ( 130 NOS. OF TAP DISCONNECTED ) | Kollam WS Sub Dn - AEE | |
| 15 Feb 2024 | SITE HANDED OVER | Kollam WS Sub Dn - AEE | |
| 15 Feb 2024 | SITE HANDED OVER | Kollam WS Sub Dn - AEE |