Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Sep 2024 Package 1- 100 % COMPLETED, Final Bill submitted. Package 2-100 % disconnected - 347 nos out of 347 nos. completed. Final Bill submitted. Kollam WS Sn 2 - AE
02 Sep 2024 Package 1- 100 % COMPLETED, Final Bill submitted. Package 2-100 % disconnected - 347 nos out of 347 nos. completed. Bill under preparation. Kollam WS Sn 2 - AE
29 Aug 2024 Package 1- 100 % COMPLETED, Final Bill submitted. Package 2-100 % disconnected - 347 nos out of 347 nos. completed. Bill under preparation. Kollam WS Sn 2 - AE
22 Aug 2024 Package 1- 100 % COMPLETED, Final Bill submitted. Package 2-100 % disconnected - 347 nos out of 347 nos. completed. Bill under preparation. Kollam WS Sn 2 - AE
16 Aug 2024 Package 1- 100 % COMPLETED, Final Bill submitted. Package 2- 97 % disconnected - 339 nos out of 347 nos. completed. Work in progress Kollam WS Sn 2 - AE
13 Aug 2024 Package 1- 279 nos. disconnected -79% completed. . Package 2- 90 % disconnected - 315 nos out of 347 nos. completed. Work in progress Kollam WS Sn 2 - AE
10 Aug 2024 Package 1- 279 nos. disconnected -79% completed. . Package 2- 88 % disconnected - 306 nos out of 347 nos. completed. Work in progress Kollam WS Sn 2 - AE
06 Aug 2024 Package 1- 279 nos. disconnected -79% completed. . Package 2- 88 % disconnected - 306 nos out of 347 nos. completed. Work in progress Kollam WS Sn 2 - AE
01 Aug 2024 Package 1- 279 nos. disconnected -79% completed. . Package 2- 86 % disconnected - 300 nos out of 347 nos. completed. Work in progress Kollam WS Sn 2 - AE
29 Jul 2024 Package 1- 279 nos. disconnected -79% completed. . Package 2- 86 % disconnected - 300 nos out of 347 nos. completed. Work in progress Kollam WS Sn 2 - AE