| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Jun 2024 | Package 1- 200 nos. disconnected -60% completed. . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors . | Kollam WS Sn 2 - AE | |
| 19 Jun 2024 | Package 1- 200 nos. disconnected -60% completed. . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors . | Kollam WS Sn 2 - AE | |
| 19 Jun 2024 | Package 1- 170 nos. disconnected -40% . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors . | Kollam WS Sn 2 - AE | |
| 15 Jun 2024 | Package 1- 170 nos. disconnected -40% . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors . | Kollam WS Sn 2 - AE | |
| 14 Jun 2024 | Package 1- 170 nos. disconnected -40% . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. | Kollam WS Sn 2 - AE | |
| 10 Jun 2024 | Work restarted, But due to water logging area excavation is difficult and affects the progress of work. Package 1- 170 nos. disconnected -40% . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. | Kollam WS Sn 2 - AE | |
| 05 Jun 2024 | Work restarted, But due to water logging area excavation is difficult and affects the progress of work. Package 1- 170 nos. disconnected -40% package 2- 55 % disconnected - 191 nos out of 347 nos.completed. | Kollam WS Sn 2 - AE | |
| 01 Jun 2024 | Due to continuous rain and heavy water logged areas , exception is not possible. Hence Work not possible.Time of extension application submitted. | Kollam WS Sn 2 - AE | |
| 28 May 2024 | Due to heavy and continuous rain work progress is slow | Kollam WS Sn 2 - AE | |
| 25 May 2024 | Work started, but huge interruptions are raised from public and they not allow to cut the strret tap. This matter informed to Dn. Councilor, Deputy mayor. | Kollam WS Sn 2 - AE |