Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jun 2024 Package 1- 200 nos. disconnected -60% completed. . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors . Kollam WS Sn 2 - AE
19 Jun 2024 Package 1- 200 nos. disconnected -60% completed. . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors . Kollam WS Sn 2 - AE
19 Jun 2024 Package 1- 170 nos. disconnected -40% . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors . Kollam WS Sn 2 - AE
15 Jun 2024 Package 1- 170 nos. disconnected -40% . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors . Kollam WS Sn 2 - AE
14 Jun 2024 Package 1- 170 nos. disconnected -40% . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Kollam WS Sn 2 - AE
10 Jun 2024 Work restarted, But due to water logging area excavation is difficult and affects the progress of work. Package 1- 170 nos. disconnected -40% . Package 2- 64 % disconnected - 221 nos out of 347 nos.completed. Kollam WS Sn 2 - AE
05 Jun 2024 Work restarted, But due to water logging area excavation is difficult and affects the progress of work. Package 1- 170 nos. disconnected -40% package 2- 55 % disconnected - 191 nos out of 347 nos.completed. Kollam WS Sn 2 - AE
01 Jun 2024 Due to continuous rain and heavy water logged areas , exception is not possible. Hence Work not possible.Time of extension application submitted. Kollam WS Sn 2 - AE
28 May 2024 Due to heavy and continuous rain work progress is slow Kollam WS Sn 2 - AE
25 May 2024 Work started, but huge interruptions are raised from public and they not allow to cut the strret tap. This matter informed to Dn. Councilor, Deputy mayor. Kollam WS Sn 2 - AE