| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Aug 2021 | Work ressumed and in Progress | Thodupuzha PH Dn EE | |
| 27 Jul 2021 | Work is temporarily stopped due to heavy rain in the area | Devikulam AE | |
| 20 Jul 2021 | Given 3 more connections, Now FHTC completed is 75 | Devikulam AE | |
| 20 Jul 2021 | To be restarted | Thodupuzha PH Dn EE | |
| 11 Jul 2021 | Had a joint inspection with NH AE regarding permissions for pipe relaying along NH 85 on 09/07/21 | Devikulam AE | |
| 05 Jul 2021 | CC 3rd and Part Bill for remaining 46 Connections out of completed is submitted to subdivision | Devikulam AE | |
| 28 Jun 2021 | 72 FHTCs Completed. Work delayed due to pandemic related issues and NH Permission issues. | Devikulam AE | |
| 19 Jun 2021 | 72 FHTCs Completed. Work delayed due to pandemic related issues and NH Permission issues. | Devikulam AE | |
| 10 Jun 2021 | As of now 72 FHTCs Completed. Work delayed due to pandemic related issues and NH Permission issues. | Devikulam AE | |
| 04 Jun 2021 | 72 connections given | Thodupuzha PH Dn EE |