| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Jun 2022 | Work in Progress | Devikulam AE | |
| 21 May 2022 | Work is temporarily halted due to heavy rain in the area | Devikulam AE | |
| 10 May 2022 | Work in progress | Devikulam AE | |
| 26 Apr 2022 | Work in progress for 2 more new connections | Devikulam AE | |
| 18 Apr 2022 | 3 more connections given. Geo-tagging to complete | Devikulam AE | |
| 05 Apr 2022 | Work in progress | Devikulam AE | |
| 29 Mar 2022 | Work in progress | Devikulam AE | |
| 24 Mar 2022 | Work in progress. Finding difficulty to find more consumers/connections from the existing distribution lines since no additional pipe laying included in the schedule | Devikulam AE | |
| 15 Mar 2022 | Work in progress | Devikulam AE | |
| 10 Mar 2022 | Had a joint inspection with NH Authorities at the leakage location. NH authorities advised to relay the pipes along sides of the road. | Devikulam AE |