| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Sep 2021 | 9 more connections completed | Devikulam AE | |
| 21 Sep 2021 | Pipe relaying works along NH continues. Water Connection works are also in progress | Devikulam AE | |
| 16 Sep 2021 | 4 new connection given. Pipe relaying work at 14th mile (near Culvert) along NH 85 also completed. | Devikulam AE | |
| 09 Sep 2021 | 1 more Connection added. Pipe relaying works along Highway is about to start | Devikulam AE | |
| 05 Sep 2021 | Given 5 more connections. Geo-tagging to be completed | Devikulam AE | |
| 27 Aug 2021 | Work restarted on 26/08/21 | Devikulam AE | |
| 23 Aug 2021 | Work in Progress. NH authorities advised to start work along NH after District collector's trenching ban. Also contractor halted the work due to festival holidays | Devikulam AE | |
| 17 Aug 2021 | Work in Progress. NH authorities advised to start work along NH after District collector's trenching ban. They also demanded to start work only in presence of their officials | Devikulam AE | |
| 10 Aug 2021 | Work in Progress. Had discussion with NH Authority regarding Pipe relaying along NH 85. According to the suggestions by NH officials, relaying work is about to start. | Devikulam AE | |
| 04 Aug 2021 | Given 2 more connections, Now FHTC completed is 77 | Devikulam AE |