| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Mar 2022 | Zone 2 Pipe line charged. Observed Water leakage in 140mm dia PVC pipe placed the middle of NH 85 at Culvert located in Machiplavu, Adimaly. Pipe had broken during culvert widening works by NH Authorities. Pipe need to be re-laid along the sides of widened culvert. Need additional work | Devikulam AE | |
| 17 Feb 2022 | Preparation for Charging Zone 2 of RWSS in Progress | Devikulam AE | |
| 09 Feb 2022 | In order to find new connections we have to charge Zone 2 Region of RWSS to Adimaly Scheme. Preparation works for charging Zone 2 Region is in progress. More relaying works required along NH 85 | Devikulam AE | |
| 03 Feb 2022 | 140mm PVC & 125mm GI Pipe Relaying works as per the schedule completed | Devikulam AE | |
| 29 Jan 2022 | 140mm PVC Relaying work along NH 85 at 14th Mile Adimaly in progress | Devikulam AE | |
| 19 Jan 2022 | Work in progress | Devikulam AE | |
| 12 Jan 2022 | 3 more connection added. FHTCs now comes to 104 | Devikulam AE | |
| 04 Jan 2022 | Work along NH85 is about to restart | Devikulam AE | |
| 28 Dec 2021 | Work in progress | Devikulam AE | |
| 20 Dec 2021 | Work in progress | Devikulam AE |