| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Jul 2024 | Package I- Pipeline works halted because of rain. Package II-Work order issued to Sri. K.S. Balakrishna Pillai on 21/06/2024. | Kattappana AEE 1 | |
| 30 Jun 2024 | Package I- Pipeline works halted because of rain. Package II-Work order issued to Sri. K.S. Balakrishna Pillai on 21/06/2024. | Kattappana AEE 1 | |
| 27 Jun 2024 | Package I- Pipeline works halted because of rain. Package II-Work order issued to Sri. K.S. Balakrishna Pillai on 21/06/2024. | Kattappana AEE 1 | |
| 24 Jun 2024 | Package I- Pipeline works halted because of rain. Package II-Work order issued to Sri. K.S. Balakrishna Pillai on 21/06/2024. | Kattappana AEE 1 | |
| 21 Jun 2024 | Package I- Road restoration works are ongoing at Vallakkadavu and Kunthalampara site. Package II-For tender acceptance. | Kattappana AEE 1 | |
| 18 Jun 2024 | Package I- Pipeline works halted because of rain. Package II-For tender approval. | Kattappana AEE 1 | |
| 15 Jun 2024 | Package I- Pressure test works are ongoing. Package II-For tender approval. | Kattappana AEE 1 | |
| 12 Jun 2024 | Package I- Pressure test works are ongoing. Package II-For tender approval. | Kattappana AEE 1 | |
| 09 Jun 2024 | Package I- Pipeline works halted because of rain. Package II-For tender approval. | Kattappana AEE 1 | |
| 06 Jun 2024 | Package I- Pipeline works halted because of rain. Package II-For tender approval. | Kattappana AEE 1 |