| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 May 2024 | Package I- So far, laid 6132.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 04 May 2024 | Package I- So far, laid 4171.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 04 May 2024 | Package I- So far, laid 4171.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 01 May 2024 | Package I- So far, laid 4171.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 28 Apr 2024 | Package I- Road restoration works are ongoing at Kunthalampara site. Package II-For tender approval. | Kattappana AEE 1 | |
| 25 Apr 2024 | Package I- So far, laid 3403 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 22 Apr 2024 | Package I-Pipeline works are ongoing. Package II-For tender approval. | Kattappana AEE 1 | |
| 19 Apr 2024 | Package I- So far, laid 2683 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 16 Apr 2024 | Package I- So far, laid 2185 metres of 160 mm PVC pipe and 23.5 metres of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 13 Apr 2024 | So far, laid 1919 meters of 160 mm PVC pipes and 23.5 meters of 150mm GI pipes. Package II-For tender approval. | Kattappana AEE 1 |