03 Jun 2024 Package I- Pipeline works halted because of rain. Package II-For tender approval. Kattappana AEE 1
31 May 2024 Package I- Road restoration works are ongoing. Package II-For tender approval. Kattappana AEE 1
28 May 2024 Package I- Road restoration works are ongoing. Package II-For tender approval. Kattappana AEE 1
25 May 2024 Package I- Pipeline works are ongoing. Package II-For tender approval. Kattappana AEE 1
22 May 2024 Package I- Pipeline works are ongoing. Package II-For tender approval. Kattappana AEE 1
19 May 2024 Package I- Pipeline works are ongoing. Package II-For tender approval. Kattappana AEE 1
16 May 2024 Package I- So far, laid 7887.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. Kattappana AEE 1
13 May 2024 Package I- So far, laid 7533.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. Kattappana AEE 1
10 May 2024 Package I- So far, laid 6858.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. Kattappana AEE 1
10 May 2024 Package I- So far, laid 6858.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. Kattappana AEE 1