| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Jun 2024 | Package I- Pipeline works halted because of rain. Package II-For tender approval. | Kattappana AEE 1 | |
| 31 May 2024 | Package I- Road restoration works are ongoing. Package II-For tender approval. | Kattappana AEE 1 | |
| 28 May 2024 | Package I- Road restoration works are ongoing. Package II-For tender approval. | Kattappana AEE 1 | |
| 25 May 2024 | Package I- Pipeline works are ongoing. Package II-For tender approval. | Kattappana AEE 1 | |
| 22 May 2024 | Package I- Pipeline works are ongoing. Package II-For tender approval. | Kattappana AEE 1 | |
| 19 May 2024 | Package I- Pipeline works are ongoing. Package II-For tender approval. | Kattappana AEE 1 | |
| 16 May 2024 | Package I- So far, laid 7887.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 13 May 2024 | Package I- So far, laid 7533.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 10 May 2024 | Package I- So far, laid 6858.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 | |
| 10 May 2024 | Package I- So far, laid 6858.4 meters of 160 mm class 5 PVC pipe and 23.5 meters of 150mm GI pipe. Package II-For tender approval. | Kattappana AEE 1 |