| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Oct 2024 | Package I- Distribution pipeline works are ongoing. Package II-Agreement executed on 23.09.2024. | Kattappana AEE 1 | |
| 15 Oct 2024 | Package I- Distribution pipeline works are ongoing. Package II-Agreement executed on 23.09.2024. | Kattappana AEE 1 | |
| 12 Oct 2024 | Package I- Distribution pipeline works are ongoing. Package II-Agreement executed on 23.09.2024. | Kattappana AEE 1 | |
| 18 Oct 2024 | Package I- Pipeline works halted because of rain. Package II-Agreement executed on 23.09.2024. | Kattappana AEE 1 | |
| 15 Oct 2024 | Package I- Pipeline works halted because of rain. Package II-Agreement executed on 23.09.2024. | Kattappana AEE 1 | |
| 12 Oct 2024 | Package I- Pipeline works halted because of rain. Package II-Agreement executed on 23.09.2024. | Kattappana AEE 1 | |
| 12 Oct 2024 | Agreement executed on 23.09.2024. | Kattappana AEE 1 | |
| 09 Oct 2024 | Package I- Pipeline works halted because of rain. Package II-Work order issued to Sri. K.S. Balakrishna Pillai on 21/06/2024. | Kattappana AEE 1 | |
| 06 Oct 2024 | Package I- Pipeline works halted because of rain. Package II-Work order issued to Sri. K.S. Balakrishna Pillai on 21/06/2024. | Kattappana AEE 1 | |
| 03 Oct 2024 | Package I- Pipeline works halted because of rain. Package II-Work order issued to Sri. K.S. Balakrishna Pillai on 21/06/2024. | Kattappana AEE 1 |