Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Mar 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work seperately arranged Perlassery Sn 2 AE
22 Mar 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work seperately arranged Perlassery Sn 2 AE
18 Mar 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work seperately arranged Perlassery Sn 2 AE
14 Mar 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted Perlassery Sn 2 AE
09 Mar 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted Perlassery Sn 2 AE
04 Mar 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted Perlassery Sn 2 AE
27 Feb 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted Perlassery Sn 2 AE
21 Feb 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted Perlassery Sn 2 AE
17 Feb 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted Perlassery Sn 2 AE
10 Feb 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted Perlassery Sn 2 AE