Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Dec 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
07 Dec 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
25 Nov 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
18 Nov 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
09 Nov 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
27 Oct 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
21 Oct 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
12 Oct 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
03 Oct 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
27 Sep 2023 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE |