Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Dec 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
07 Dec 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
25 Nov 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
18 Nov 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
09 Nov 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
27 Oct 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
21 Oct 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
12 Oct 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
03 Oct 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
27 Sep 2023 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE