16 Aug 2021 872 FHTC has been effected including 60nos arranged by quotation Kollam PH Dn EE
14 Aug 2021 830 FHTC has been effected including 60 nos arranged by quotation and bill for total 673 FHTC has been submitted. Kollam PH Dn EE
14 Aug 2021 830 FHTCs has been effected till 14.08.21 and Bill has been submitted. . Kollam PH Dn EE
07 Aug 2021 801 FHTCs has been effected till 06.08.21 739 FHTCs has been Geo tagged and approved till 06.08.21 Bill of 523 FHTCs has been submitted. Bill of another 150 FHTCs has been prepared and will be submitted to sub division on 11.08.21 Measurement of another 66 FHTCs has been recorded on M Book. Kollam PH Dn EE
05 Aug 2021 775 FHTCs has been effected till date. Bill of 523 FHTCs has been submitted and Bill of another 151 FHTCs has been prepared. Delay in preparing bill is due to unavailability of Geo tagging site. Kollam PH Dn EE
28 Jul 2021 641 FHTCs has been effected till date. Bill of 523 FHTCs has been submitted. Delay in preparing bill is due to unavailability of Geo tagging site. Kollam PH Dn EE
20 Jul 2021 591 FHTCs has been effected till date. Bill of 372 FHTCs has been submitted. Bill of another 150 FHTCs is preparing and delayed due to Geo tagging issues. Now rectified Kollam PH Dn EE
06 Jul 2021 452 FHTCs has been effected till date. Bill of 372 FHTCs has been already been submitted. Kollam PH Dn EE
28 Jun 2021 400 FHTCs have been effected till date. Bill of 372 FHTCs have already been submitted Kollam PH Dn EE
12 Jun 2021 372 FHTCs has been effected till date and bill of those 372 FHTCs have been submitted. A bill amount of Rs.37.67 lakhs have been claimed. New FHTCs are not effecting as panchayath officials denied permission to cut panchayath tar/concrete roads. A letter has been given to sub division explaining the difficulties in providing FHTCs Kollam PH Dn EE