Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Jul 2021 | total geotagged connection 411 | Kollam Project Dn AE | |
30 Jul 2021 | Total FHTC given 402 | Kollam Project Dn AE | |
28 Jul 2021 | Total connection given 563 geotagged 391 | Kollam Project Dn AE | |
24 Jul 2021 | 366 FHTC COMPLETED And 10319m laying Completed | Kollam Project Dn AE | |
19 Jul 2021 | 313 FHTC completed and 8800m laying completed | Kollam Project HD | |
01 Jul 2021 | 245 FHTC completed and 8800m laying completed | Kollam Project HD | |
29 Jun 2021 | 243 FHTC completed and 8800m laying completed | Kollam Project Dn AE | |
17 Jun 2021 | 163 fhtc given | Kollam Project HD | |
16 Jun 2021 | 148 FHTC GIVEN | Kollam Project HD | |
10 Jun 2021 | 138 fhtc given | Kollam Project HD |