Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Sep 2021 | Total geotagged connections 550 | Kollam Project Dn AE | |
09 Sep 2021 | 533 FHTC GIVEN | Kollam Project HD | |
05 Sep 2021 | 504 connection geotagged | Kollam Project Dn AE | |
30 Aug 2021 | 481 connections geotagged and 14km laying completed | Kollam Project Dn AE | |
27 Aug 2021 | 470 connections Gotagged 13.1km laying done | Kollam Project HD | |
24 Aug 2021 | 463 connections geotagged and 13.1 km laying completed | Kollam Project Dn AE | |
17 Aug 2021 | 455 connections geotagged and 13.1 km laying completed | Kollam Project Dn AE | |
13 Aug 2021 | 450 connections geotagged and 12.55 km laying completed | Kollam Project Dn AE | |
12 Aug 2021 | 450 CONNECTIONS GIVEN | Kollam Project HD | |
04 Aug 2021 | Total geotagged connection 444 numbers. | Kollam Project Dn AE |