Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Jan 2023 | Pipe laying and HTC connection work progressing. FHTC completed -1726 | Kollam Project Dn AE | |
17 Dec 2022 | Pipe laying and FHTC work progressing. Vilakkudy Temple - Kulapuram road (node : 410-413-422 )90mm/8kg laying | Kollam Project Dn AE | |
13 Dec 2022 | Pipe laying and FHTC work progressing. 63mm, 10kg and 63mm, 8kg PVC pipe laying work at Mannamkuzhi | Kollam Project Dn AE | |
09 Dec 2022 | Pipe laying and FHTC work progressing. 90mm ,8kg pipe pressure Testing paparamcode - mannamkuzhi road | Kollam Project Dn AE | |
08 Dec 2022 | Pipe laying and FHTC work progressing. 90mm ,8kg pipe laying at Paparamcode - Mannamkuzhi road and Kunnicode- saleem hotel branch road. | Kollam Project Dn AE | |
07 Dec 2022 | Pipe laying and FHTC work progressing. 90mm ,8kg pipe laying at Paparamcode - Mannamkuzhi road(node 373-380) and Kunnicode- saleem hotel branch road. | Kollam Project Dn AE | |
02 Dec 2022 | Pipe laying and FHTC work in progressing. 90mm ,8kg pipe laying at paparamcode - mannamkuzhi road | Kollam Project Dn AE | |
28 Nov 2022 | Pipe laying work progressing | Kollam Project Dn AE | |
16 Sep 2022 | 250mm DI Distribution Work progressing at Elampal | Kollam Project Dn AE | |
12 Sep 2022 | Work progressing at Manjamankala Uricode Culvert crossing DI 300mm... | Kollam Project Dn AE |