Status Date Overall Project Status Project Officer Contact
10 Mar 2023 pack-1 Work in progress | 70% Completed | 10/03/2023 1) 11 LL OHSR at JTS – cover slab and beam reinforcement work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed PACK-2 Not Started | 10/03/2023 Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023 PACK-4 Not Started | 10/03/2023 Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023 PACK-3 Work in progress | 91% Completed | 10/03/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall THIRD lift Concrete work completed. inside column work proressing 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara PACK-5 Not Started | 10/03/2023 The work is foreclosed Chittur Project Dn - AE 2
10 Mar 2023 Work in progress | 76% Completed | 10/03/2023 Supplied total -84.753km, Laid Total-63.706 KM,/out of 90km , FHTC -2378/out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.630km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
03 Mar 2023 Work in progress | 76% Completed | 03/03/2023 Supplied total -84.753km, Laid Total-63.706 KM,/out of 90km , FHTC -2358/out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.566km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
24 Feb 2023 Work in progress | 76% Completed | 24/02/2023 Supplied total -84.753km, Laid Total-63.706 KM,/out of 90km , FHTC -2335/out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.566km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
17 Feb 2023 Work in progress | 76% Completed | 17/02/2023 Supplied total -84.753km, Laid Total-63.706 KM,/out of 90km , FHTC -2312/out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.566km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
10 Feb 2023 Work in progress | 76% Completed | 10/02/2023 Supplied total -84.753km, Laid Total-63.706 KM,/out of 90km , FHTC -2286/out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.566km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
03 Feb 2023 Work in progress | 75% Completed | 30/01/2023 Supplied total -84.753km, Laid Total-63.656 KM,/out of 90km , FHTC -2278/out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.566km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
20 Jan 2023 Work in progress | 75% Completed | 20/01/2023 Supplied total -84.753km, Laid Total-61.266 KM, FHTC -2276 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.566km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
13 Jan 2023 Work in progress | 75% Completed | 13/01/2023 Supplied total -84.753km, Laid Total-61.266 KM, FHTC -2491 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.566km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
06 Jan 2023 Work in progress | 75% Completed | 06/01/2023 Supplied total -84.753km, Laid Total-61.266 KM, FHTC -2233 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.566km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M (4th bill-170 FHTC provided)) Chittur Project Dn - AE 2