JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8

Project JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Project Code PKDJJM12206095
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 183000000
AS Number G.O(Rt) No 777/2020/WRD
TS Amount (Rs) 147400000
TS Number TS/2020-2021/2020/2260
Total Bill Submitted (Rs) 62725380
Total Bill Paid (Rs) 62725380
Population Benefitted 36031
Capacity in MLD 0.00
Actual Project Completion Date 31 Dec 2024
Coverage Marutharoad panchayath - Zone 7 and 8

Packages

No. Project Name Location View
1 JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8 Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jun 2024 Work in progress | 82% Completed | 20/06/2024 Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2499 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
12 Jun 2024 Work in progress | 82% Completed | 12/06/2024 Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2499 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
06 Jun 2024 Work in progress | 82% Completed | 06/06/2024 Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2077 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
23 May 2024 Work in progress | 82% Completed | 23/05/2024 Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2077 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
16 May 2024 Work in progress | 82% Completed | 16/05/2024 Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2077 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 12/05/2021
Scheduled date of Completion of the Project 11 Oct 2021
Expected date of Completion 31/12/2023

Processing Dates

AS Date 24 Dec 2020
TS Date 01 Jan 2021